Project application : Submit the project feasibility study report By the national development and reform commission to prepare and issue project registration slip
Early stage of the project survey : Project to carry on the preliminary survey, to project power supply bureau for record and issue a grid
Project drawings : Design project components, electrical, and the power distribution ark is a secondary wiring diagram, power supply bureau plan approval
Construction of the : Project construction and according to the figure construction, plant commissioning report issued by the completion of the engineering
Grid acceptance : Power supply bureau to grid acceptance of power station, dual phase meter
operations : Power plant operation, plant for daily maintenance, maintenance, cleaning components, ensure the normal operation of power plant |